Szczegóły ogłoszenia o przetargu
Status
Data przesłania
26/04/2019
Data odpowiedzi
02/05/2019
Język
Status
Udzielona odpowiedź
Szczegóły pytania
Temat
Task 6:
Pytanie
Given the description of the requirements described in the TS and the existing platforms that give access to Sentinel data and their derived products, what is expected to be accomplished in the frame of the present Contract?
Odpowiedź
02/05/2019
Sentinel (2 A/B) data are ‘only’ the source for the HR VPP products and are not part of the deliverables of this product. Task 6 is about making HR VPP products accessible to Copernicus users in a harmonised manner, at least across CLMS biophysical parameter products. Whether it makes sense to use mechanisms already available at an existing platform ultimately depends on the choice of the platform.