Detalii întrebare
DR Data Replication Mode
Is not clear in the tender documentation the replica synchronization mode between Production and DR environment. Should data replication be synchronous or asynchronous?
09/07/2019
The answer is asynchronous, as the environments shall remain fully separated during normal operation. The details on the communication requirements for data replication between disaster and recovery environment are to be detailed by the contractor within the Disaster recovery plan that is to be included in the CPS. Please compare with answers to question 64 and 65, Point 3.