Number of projects at each phase
Fråga
The Annex V : BUDGET indicates clearly the number of projects: - 20 projects identified - 10 projects for prefeasibility studies - 5 feasibility studies. Nevertheless, the ToR leave interpretation for higher number: ToR §4.2.1 (page 10): "The Consultant will identify and propose a pipeline of AT LEAST 20 candidate projects..." ToR §4.2.1 (page 11): "...the consultant will recommend the selection of AT LEAST 10 projects for pre-feasibility". Please confirm the number of projects to be studied at each phase.
Svar
04/11/2019
The consultant may identify and propose more than the minimum number of projects at each stage allowing the Contracting Authority to make a selection of the 10/5 projects for pre-feasibility studies and feasibility studies.