Bidder's Management Plan Description (1.1.4 of the Tender Specification)
The specifications require the presentation of a management plan, should that be a complete and self- standing document, or only a description of the management procedure that will be adopted during the project implementation? If a complete and self- standing document is required, could it be added as an annex?
24/11/2015
In the Tender Specifications, Section 1.1.4 it is listed what shall be included in the Management Plan. It could be a self-standing document (annex) or a section inserted in the technical offer. The management plan shall however clearly describe the approach/methodology chosen to achieve the stated goals and to implement the project. A possible study logic is proposed with the Tender Specifications, however the tenderer can modify/adapt this proposal in order to recommend a more effective approach for the implementation of the study.