Central Heating Installation / Divider
What is the CH capacity of the existing CH group Ventilation?
30/03/2017
The CH capacity is unknown; an estimation of the existing installation has been made: - 9 pieces air heater 25.500 Watt  total 230 kW; - 3 pieces air heater GEA 31,6 kW  total 96 kW; - Air Handling Unit assembly room 60 kW; - Air Handling Unit Fuel Cell laboratory 18,3 kW; - Air Handling Unit Single Cell laboratory 94 kW; - 4 pieces air heaters Single Cell laboratory  total 43 kW; - Reformer room approx. 48 kW. - Total of the above approx. 590 kW Results calculation including starting points: - dT = 30 K; - water amount = 4,66 kg/s; - pressure loss 53 kPa.