Subject
In technical specifications 1.6. OTHER REQUIREMENTS, 9 you mention that the contractor undertake to inform the Agency in writing, as quickly as possible, of any occupational accident suffered ... etc
Question
How this could be the responsibility of the contractor provided that interims will be working under the supervision of EASO?
Answer
07/11/2017
Interim agents do not have any contractual relationship with EASO and shall therefore report to the contractor only. It is the contractor responsibility to inform EASO of any occupational accident suffered, using the communication details indicated in Article I.8 of the draft Framework Contract