Subject
Article II.18.1(j), (k) or (l) or in Article II.18.2. Draft Contract
Question
Dear Sir/ Madam, As you have write: "“The contractor is liable for damage incurred by the contracting authority as a result of the termination of the FWC or a specific contract including the cost of appointing another contractor to provide or complete the services, unless the damage was caused by the situation specified in Article II.18.1(j), (k) or (l) or in Article II.18.2. The contracting authority may claim compensation for such damage.” What kind of cost? How the Contractor should we count this cost? There is no rules or conditions.
Answer
25/06/2018
The maximum amount of the contractor liability for any loss or damage caused to the contracting authority during or as a consequence of implementation of the FWC, including in the event of subcontracting is indicated in ARTICLE II.6 LIABILITY of the Draft Contract.