Call for tenders' details

Title:
Housing/Hosting Services for a Business Continuity DataCentre
Contracting authority:
European Maritime Safety Agency
TED publication date:
06/04/2020
Time limit for receipt of tenders:
11/05/2020
Status:
Closed
Status
15/04/2020
22/04/2020
English (en)
Question details
Questions - Part I
3. What’s the maximum time that EMSA BCF (Madrid) systems could remain shutdown to perform the move?
22/04/2020
EMSA BCF systems should not stay in shutdown for more than 10 calendar days. The longer the shutdown time, the longer is the risk for EMSA. Therefore, move plans with shorter downtime will be better rewarded in the quality criteria associated with the move.