Call for tenders' details

Title:
Housing/Hosting Services for a Business Continuity DataCentre
Contracting authority:
European Maritime Safety Agency
TED publication date:
06/04/2020
Time limit for receipt of tenders:
11/05/2020
Status:
Closed
Status
27/04/2020
05/05/2020
English (en)
Question details
Power: upgrades and downgrades at contract renewal
The FWC, on I.3.3, states that "The FWC is concluded for a period of 48 months", and on I.3.5 that "The FWC is renewed automatically up to two times for a period of 12 months each time". The Tender Specifications, on section "2.1 - Power and cooling" states that "before any contract renewal (typically on a yearly basis)" power consumption baseline can be upgraded or downgraded. Does this mean that we can consider power upgrades or downgrades on the "annual contract anniversary"?
05/05/2020
Power upgrades and downgrades shall be considered on a yearly basis (i.e., annual contract anniversary). The reference to "contract renewal" on point 2.1. "Power and cooling" of the Tender Specifications is a clerical error and shall be read as "annual contract anniversary".