Subject
Question regarding criteria relating to tenders
Question
Hello! You have written that the project template in the standard reply form should be used for providing evidence regarding A1 and A2 projects. Please confirm that you only need these to be filled for A1 and A2 projects, but NOT for A3, A4, and A5 projects, and that for A3-A5 projects only the sample documents are required. Best regards,
Answer
17/06/2020
Please disregard the earlier reply. The correct answer is: Your understanding is correct.
17/06/2020
The CVs of the core team will be used to assess the criteria relating to the team delivering the service. CVs of back up specialists can be taken into account for award criterion 3 of Part B – Tender Specifications.