Question details
Subject
Number of final reports in the price list.
Question
In the technical specifications, point F. Final report, it is stated that there is only one final report. However, in the price list, the weighting is 50, meaning 1 report per school. As the reports per school are included in the remote evaluation, I am a bit confused. Should the weighting not be "1" final report, instead of "50"?
Answer
09/09/2020
After verification, we confirm that indeed the weighting of item F of the price schedule is wrong, and should read 1 instead of 50. We are updating the document in e-Tendering accordingly.