Call for tenders' details

Title:
Supply, installation and maintenance of 2 battery storage systems - 2 lots.
Contracting authority:
European Commission, Joint Research Centre (JRC)
TED publication date:
31/07/2015
Time limit for receipt of tenders:
28/09/2015
Status:
Closed
Status
08/09/2015
09/09/2015
italiano (it) English (en)
Question details
Question to the delivery time of BESS
Given that the two months of delivery of the materials are essential (see the answer to question 22), the normal time of production and delivery of Battery inverters and others exceed these time frame, we ask whether it is possible to ensure [confirm] that, by the expiration of those two months, it is sufficient only to state that the goods are ready at the site of production (thus excluding the time of delivery to the final site and the pre-assembly).
09/09/2015
Please refer to the supplementary answer to the question 22